10 December 2010

December Progress

Yesterday we passed our framing/plumbing inspection, so things are really kicking into high gear.  First the stucco goes on, then the roof and insulation, then the sheetrock.  Here's step one of the stucco application, the felt paper and metal lath.






 
Note the newly stained posts and ceiling in that last picture, here's another view below.

 

This past week Willie our trim carpenter put in stain grade trim around the windows for the 3/4" bullnose sheetrock returns.  That doesn't mean much without a picture, but I'll wait til the sheetrock is installed for pictures.  We ordered a 3 panel shaker style mahogany door and jamb, the 3 panels will be reeded glass.   The jamb arrived today so we'll get that installed and the final window above it shortly.  I added niches to the master shower which will be tiled.  Also the fiberglass pan for the shower was installed.  We decided to go with a frameless full length glass door for this shower.


Our cabinets are being made.  We are using a combination of cherry, walnut, and paint grade wood for the various rooms.  Mark the cabinet maker brought by wood samples today so Larry the painter can put sample colors on for final selection.

No comments:

Post a Comment